Floodlight towers at the Di Febo stadium: variation approved, cost rises to €179,357.88

Record no.2026/3635
Publication date26 October 2026
Publication expiry10 November 2026
Amount · amount stated in the act€179,357.88
AwardeeCity Green Light S.p.A.

What changes

The Municipality approves the variation of the works for the floodlight towers at the "U. Di Febo" sports facility. The total cost of the intervention is €179,357.88. The approved executive project was €118,037.00: the contract increase is €28,153.82, below the 50% limit (€59,018.50). A further €29,357.88 must be committed, on top of the €150,000.00 already committed.

To be checked

The tender discount is 0.2% (€292.38). The act notes that the company Lumagest S.r.l. was absorbed by City Green Light S.p.A. with effect from 1 September 2026. Among the items are the foundation stability check (€4,123.60) and the static test engineer's fee (1776.32 euros).

Official source

Open the official record page ↗

This record rewrites, in plain language, an act published on the Municipality of Silvi's public notice board. The summary is written from the text of the act, with automatic checks on figures and personal data. If anything differs, the original document prevails.

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record