Executive decision (determinazione dirigenziale)

Fontanelle nursery: electricity connection paid to E-Distribuzione, €1,313.37 including VAT

Record no.2026/0001514
Publication date21 September 2026
Publication expiry6 October 2026
Amount · amount stated in the act€1,313.37
AwardeeE-Distribuzione s.p.a.

What changes

The Municipality pays E-Distribuzione's invoice for the low-voltage electricity connection of the new Fontanelle nursery (a €720,000.00 PNRR project). Of €1,313.37, €1,076.53 goes to the company and €236.84 straight to the tax authority (VAT, via «split payment»).

To be checked

CIG BCD7D2EC8A. The quote is dated 02/09/2026 (protocol no. 20280), after the works completion certificate of 27/03/2026. In the text the date of the works contract is written 18/18/2024, which is not a valid date.

Official source

Open the original document ↗

This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record