Historic walls above the ring road: final works progress approved, €173,425.89 to Coproject
What changes
The town approves the fifth and final works progress report for securing the historic walls above state road 553 (landslide risk). Coproject is owed €173,425.89 plus VAT. Works finished on 06/08/2026, with 40 extra days for minor finishing. Project worth €995,000.00, paid with state grants.
To be checked
The contract was €533,079.18 (25.23% discount). After two variations (2025 and decision no. 458 of 2026) it rose to €709,443.81: €176,364.63 more, about +33%. This act does not explain the reasons for the variations. CIG B150D756ED.
Official source
This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.
If anything in this record does not match the original document, write to us: we will correct it and say so.
Report a mistake in this record