Executive decision (determinazione dirigenziale)

Casoli school: executive-design documents updated, total project cost unchanged

Record no.2026/0001593
Publication date1 October 2026
Publication expiry16 October 2026
Amount · amount stated in the act€2,600,000.00

What changes

To take part in the national call for seismic-risk prevention in Inner Areas, the municipality updates some technical documents of the demolition-and-rebuild project for the Casoli infant and primary school, at the request of the ministerial Commission (procedural assistance request). The project's total cost stays unchanged at €2,600,000.00; the state funding has not yet been awarded.

To be checked

The act states that the ministerial Commission requested additional supporting documentation on the building's declared structural shortcomings; the project remains conditional on obtaining the state grant, not yet awarded.

Official source

Open the original document ↗

This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record