Mambelli Barnabei school: final works statement approved, €460,951 still owed to the contractor
What changes
The municipality approves the final accounting for the Mambelli Barnabei school reconstruction, carried out by Ubaldi Costruzioni S.p.A.: works totalling €4,049,731.89, of which €3,588,780.14 already paid in instalments; a residual credit of €460,951.75 plus 10% VAT remains owed to the contractor. The €5,116,110.52 project is PNRR-funded.
To be checked
The act follows six previously paid progress instalments between 2025 and 2026; the final balance is now subject to external technical-administrative sign-off.
Official source
This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.