Executive decision (determinazione dirigenziale)

Mambelli school (PNRR): spending commitments reduced by €68,194.01 after testing and final statement

Record no.2026/0001821
Publication date5 November 2026
Publication expiry20 November 2026
Amount · amount stated in the act€68,194.01
AwardeeUbaldi Costruzioni S.p.A.

What changes

After the final statement and testing of the new Mambelli Barnabei school (PNRR funding of €5,116,110.52), the Municipality cuts spending commitments by €68,194.01: €68,184.01 on contractor Ubaldi Costruzioni, €0.01 on Studio Iezzi Geologi, €9.99 on works supervision. The contractor is owed €4,579,912.41 including VAT.

To be checked

Integrated contract awarded for €4,225,542.20, later reset to €4,185,405.11 by a non-substantial variation. Works accounted at €4,049,731.89, contractor's remaining credit €460,951.75 plus VAT. The final cost breakdown shows total savings of €98,183.98.

Official source

Open the original document ↗

This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.

All records for this company in the Register →

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record