Fontanelle nursery (PNRR): final cost breakdown approved, €687,281.41 spent
What changes
The Municipality closes the accounts of the Fontanelle nursery, funded by PNRR (CUP B35E24000160006). Of the €720,000 funding, €687,281.41 was spent; €32,718.59 is left as savings. The act says works were completed on 27 March 2026 and payments finished.
To be checked
Works awarded by negotiated procedure to 5 operators: €499,385.45 plus VAT against a base of €514,714.68. The text gives a contract date "18/18/2024", which does not exist. A contract variation did not change the contract amount.
Official source
This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.
If anything in this record does not match the original document, write to us: we will correct it and say so.
Report a mistake in this record