Amount · amount stated in the act€4,225,542.20
AwardeeUbaldi Costruzioni s.p.a.

What changes

The Area Manager awards Ubaldi Costruzioni s.p.a. the detailed design and reconstruction of the Mambelli Barnabei middle school in Via Finocchi. The award amount is €4,225,542.20 excluding VAT (starting price: €4,240,922.06). The act states the financing as the PNRR, Mission 4, Investment 3.3, Next Generation EU funds.

To be checked

10 operators were invited on the telematic platform; the awardee is recorded as the only bidder, with a 0.50 percent rebate. CIG A004C50A6E and CUP B38E18000020002 are cited. The final cost of the works is not stated in this act.

Official source

The original document is not linked to this record.

This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record