Amount · amount stated in the act€5,190,721.83
AwardeeOFFICINA TECNICA S.r.l. e ATI BUZZELLI

What changes

The Municipal Executive approves two feasibility designs for a new lower secondary school: OFFICINA TECNICA's, worth 5,190,721.83 euros, and ATI BUZZELLI's, worth 5,116,110.52 euros. These are project financial frameworks, not contract amounts; the final cost is not stated.

To be checked

The first-ranked design includes 4,206,038.48 euros for works and 984,683.35 euros for sums available to the authority; the second includes 4,142,525.10 euros and 973,585.42 euros. CUP B38H23000090006. The act cites design competition CIG 965420452B.

Official source

The original document is not linked to this record.

This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.

Found a mistake?

If anything in this record does not match the original document, write to us: we will correct it and say so.

Report a mistake in this record