Detailed design of the new Mambelli Barnabei school approved
What changes
The Giunta approves the detailed design of the Mambelli Barnabei middle school in Via Finocchi (seismic upgrade by building replacement, PNRR M4C1I3.3) and amends the project sheet of the area in the detailed plan. The total cost of the work is 5,116,110.52 euros, of which 4,187,992.13 for the integrated contract and 928,118.39 set aside by the contracting authority. Unanimous vote, 6 of 6 present.
To be checked
The economic framework states 4,187,992.13 euros for the integrated contract (4,089,310.44 works and 98,681.69 detailed design); the 2023 award decision stated 4,225,542.20 euros excluding VAT. This act does not explain the change between the two amounts. The timetable is stated to be consistent with PNRR deadlines. CUP B38E18000020002.
Official source
The original document is not linked to this record.
This record rewrites, in plain language, an act published on the Municipality of Atri's public notice board. The summary was checked by a human editor against the original document.
All records for this company in the Register →
If anything in this record does not match the original document, write to us: we will correct it and say so.