The Fontanelle nursery: works finished, service still to start

On 27 March 2026 the construction site of Fontanelle's new nursery (asilo nido) was finished. On 26 June the Municipality of Atri approved the final statement; on 5 November it closed the accounts: 687,281.41 euros of PNRR funds spent out of 720,000. Yet in September, families and the opposition were still asking for an opening date, and in the documents we have read there is none. Here is what the records say, step by step, and what remains unanswered.

Infographic: 720,000 euros of funding, final spending of 687,281.41 euros, savings of 32,718.59 euros, 30 planned places and a timeline of the records from October 2024 to November 2026.
OpenCivTech infographic using data from determination 1123 of 5 November 2026.

In brief

Before and after: a school for ages 3-6, a nursery for ages 0-3

In Fontanelle, in via Giuseppe Verdi, stood the infant school, for children aged 3-6. Local press reported it on the award of the works (Ekuonews, 22 November 2024) and Prospettiva Atri did the same (9 September 2026). The PNRR project was not a refurbishment: it provided for demolishing the building and building a new one, for a different service, the nursery for ages 0-3. The planned places are 30: the figure is reported by the local press and confirmed by OpenCivTech's owner; it does not appear in determination 1123.

In the meantime the infant school has moved. Mayor Piergiorgio Ferretti confirmed on 7 September that it stays in the former primary-school premises: two classrooms of 48 and 29 square metres for about 25 children, and a 156 m² atrium. He explained that the nursery premises, funded for ages 0-3, cannot host it. According to the mayor the nursery will widen Fontanelle's offer from 0 to 10 years, also for neighbouring municipalities (press summary, not a verbatim quote).

The story, record by record

From the Ministry's notice to the last record, about two and a half years go by.

DateRecordWhat it says
15/05/2024Public notice for new projects (PNRR M4C1I1.1)Cited in determination 1123
05/09/2024Funding agreement between the Municipality and the Ministry of Education and MeritCited in determination 1123
10/10/2024Executive Committee resolution 78Approves the technical and economic feasibility project, 720,000 euros
14/10/2024Executive Committee resolution 82Approves the executive project: 514,714.68 euros of works (of which 24,963.08 safety), 51,471.47 VAT, 153,813.85 at the contracting authority's disposal
15/10/2024Determination to contract 1613Negotiated procedure without notice (art. 50, para. 1, lett. c, Legislative Decree 36/2023), lowest price, 5 operators invited
25/10/2024Determination 1678Award: 499,385.45 euros plus 10% VAT
December 2024Works contract, rep. 1673Determination 1123 reads "18/18/2024", an impossible date: the L.190 register and Dossier Zero give 18/12/2024
29/01/2025Handover of the worksCited in determination 1123
07/07/2025Executive Committee resolution 116Non-substantial contract modification (art. 120, para. 7), with no change to the contract amount
03/11/2025Determination 1332First progress statement: 174,262.63 euros plus VAT
27/02/2026Determination 202Second progress statement: 127,393.50 euros plus VAT
27/03/2026Certificate of completion of the worksCited in determination 1123
26/06/2026Determination 614Final statement and Certificate of Regular Execution: final payment certificate 97,852.23 euros plus 10% VAT
14/09/2026Act 2026/0001475 (register)Sub-commitment of 1,313.37 euros to E-Distribuzione for the nursery's electricity connection
18/09/2026 and 13/10/2026Determinations 920 and 1023Payment of an invoice for technical services of 27,219.57 euros (invoice no. 12 of 03/09/2026)
05/11/2026Determination 1123Approval of the final economic framework

Two dates, side by side, tell the story of the works: handover on 29 January 2025, completion on 27 March 2026. That is fourteen months. The first progress statement was approved nine months after handover, on 3 November 2025.

The accounts: where the 720,000 euros went

The Municipality published the final economic framework with determination 1123. Of 720,000 euros, 549,324.00 are works (VAT included) and 170,676.00 are sums at the authority's disposal: technical costs, incentives, connections, and 32,718.59 euros of savings.

ItemAmount
Works, measured and lump-sum (base)489,751.60 €
Discount offered (3.13%)−15,329.23 €
Safety costs (not subject to discount)24,963.08 €
Total works499,385.45 €
VAT on works (10%)49,938.55 €
Total works including VAT549,324.00 €
Incentives for technical functions (art. 45)6,176.59 €
Design and works supervision (fee 68,270.00 € plus contributions and VAT)86,620.98 €
Safety coordination, surveys and cadastral work27,807.72 €
Geological technical services (with contributions and VAT)5,002.38 €
Geological and geognostic surveys (with VAT)6,005.22 €
Structural testing (with contributions)4,334.15 €
Total technical-expenses contribution (B.2)129,770.45 €
Other items (ANAC fee, fire-brigade office fees, utility connections)2,010.37 €
Savings32,718.59 €
Total sums at the contracting authority's disposal170,676.00 €
Total project720,000.00 €
of which from PNRR funds687,281.41 €

We redid the sums: 549,324.00 + 170,676.00 = 720,000.00 euros; 720,000.00 − 32,718.59 = 687,281.41 euros. They add up.

Three items match data already public. Design and supervision (68,270.00 € plus 4% contributions = 71,000.80 €), safety coordination (21,707.82 € plus 5% = 22,793.21 €) and connections (1,313.37 €) are the same figures that appear in the L.190 data of the transparency portal and in act 2026/0001475.

Two calculations of our own, to be verified.

  1. The three approved works amounts (174,262.63 + 127,393.50 + 97,852.23 = 399,508.36 euros) are exactly 80% of the contract. The missing 20%, 99,877.09 euros, is the figure the L.190 register gives as "sums paid so far". It is consistent with a 20% advance, but no record we have read says so.
  2. The 2025 PIAO showed 680,353.37 euros committed; final spending is 687,281.41 euros. The difference, 6,928.04 euros, is not explained in the documents consulted.

Who carried out the works. Determination 1123 does not name the contractor. The L.190 register gives ACOTEC Costruzioni Tecnologiche S.r.l. as the awardee. Any other members of a grouping can be established only with the bid, the tender minutes and the contract, which we do not have.

September 2026: families, mayor, opposition

In early September the mothers of Fontanelle spoke to the press. What follows is reported by local newspapers and attributed to those who said it: this dossier has not verified it.

The mayor (7 and 8 September, Ekuonews and Cityrumors Abruzzo): the infant school, about 500 square metres for about 40 children across infant and primary, stays where it is; the problem, he says, is now the heat, and it concerns many schools, not only Fontanelle. The nursery will start with a management tender, which the Municipality aims to award as early as next year; the Municipality will provide the premises and the furnishings not covered by the funding. The construction site area has been cleared and new play equipment is coming shortly. He says he is available for direct discussion with parents.

Prospettiva Atri, a minority group (9 September): asks for a firm date for the start of the service, noting that the works are finished and that furnishings and the award of management are missing. It recalls a 110,000-euro application for innovative teaching furnishings, submitted in February 2026, which in its words did not obtain funding, and links the delays to the deficit and the financial recovery plan. Councillor Alessandro Graziosi is a member of that group and also the source of another OpenCivTech dossier (file 10): we say so that readers know where the criticism comes from.

The furnishings application. According to our reading of the published ranking (to be re-checked against the original document), the row for Atri (CUP B34D26003100007, 110,000 euros, submitted on 17 February 2026 as a single applicant) shows no admission status. From the documents consulted it is not clear whether it was excluded, left unfunded or admitted later, nor whether it concerns only Fontanelle or also the municipal nursery in via D'Annunzio (CUP B38H22000530006). The nursery's economic framework has no line for furnishings.

What does not appear in the documents consulted

"Does not appear" means we did not find it in the documents and pages we were able to read, not that it does not exist.

A typo in the determination

Determination 1123 gives the contract signing "on 18/18/2024": a date that does not exist. The L.190 register and Dossier Zero give 18 December 2024. It is probably a typo, to be corrected or confirmed by the Municipality.

What can be asked

Eight questions to put to the Municipality in writing, by access to records or civic access:

  1. When will the nursery open, with how many places, and by what procedure will they be assigned?
  2. When will the management notice be published and on what terms?
  3. When and at what cost will the furnishings be supplied?
  4. Has a habitability certificate been issued? Are the installation certifications available?
  5. What is the date the electricity supply was activated?
  6. Why was the 7 July 2025 modification approved and what did it change?
  7. What is the correct date of the works contract and who are the contracting companies?
  8. Which item of the economic framework does the technical-services invoice paid in 2026 refer to?

Right of reply

Replies from the Municipality and the people mentioned will be published in full on this page, with the date we received them.

Sources