Mambelli school: what the Municipality's answer to our civic access request says
On 25 September 2026 the Municipality of Atri granted our request and handed over the contract documents for the Mambelli-Barnabei school. What the documents show on the variant, on the works excluded from the PNRR, on the technical bid and on the latest progress, and what is still missing.

How to read this dossier. We report only what appears in the documents received from the Municipality, with the reference. “Not found” means “does not appear in the documents we hold”, not “does not exist”. We attribute no intentions and do not judge people: decision-makers are identified by role and by act. Personal data in the documents is not published. The Municipality and the people mentioned have the right of reply, which we publish in full. Read also the report.
What we know
- The Municipality granted the request on 25 September 2026 and made the contract documentation for the school available.
- With the variant of 30 December 2025 (determination 1610), installation works worth €445,223.88 were removed from the contract, to be financed through the Conto Termico; the contract goes from €4,089,310.44 to €4,086,723.42 (−0.06%).
- Latest progress statement received: SAL 6 at 13 July 2026, €3,485,431.51 out of €4,086,723.42 (85.3%). Completion certified on 27 July 2026.
What we do not know
- What was carried out after 13 July 2026: we do not have SAL 7, the final account, the as-built state or the test certificate.
- Which “minor works” remained after 27 July and whether they were completed by 25 September 2026.
- What the partial suspension report of 12 June 2026 says: the copy received is a scan without text, not yet read.
We ask
- The missing documents, item by item (section “Questions to the Municipality”).
- Whether the improvements in the technical bid were verified, reduced in price or formally dropped.
- Where and when the 35 trees to be provided by the Municipality will be planted.
The request and the answer
The general civic access request (art. 5(2), Legislative Decree 33/2013) was sent on 25 August 2026 and registered by the Municipality as no. 0019925 of 27 August 2026. The legal deadline, thirty days from registration, fell on 26 September.
| Date | What |
|---|---|
| 25/08/2026 | Request sent to the Municipality (copy to the regional Ombudsman) |
| 27/08/2026 | Registered as no. 0019925 |
| 01/09/2026 | Notice to the contractor as counter-interested party; no objection; deadline suspended for ten days |
| 22-23/09/2026 | Reminder by certified email, ref. 0021911 of 23/09, assigned to the General Secretariat and Public Works |
| 25/09/2026 | Answer from the Head of the Public Works Area, copied to the transparency officer: request granted |
The documentation was delivered through a transfer link active until 28 September 2026: 217 files, many digitally signed (.p7m). It includes the tender design, the bids, the tender reports, the executive design, the variant, the site handover reports, extensions and suspension, SALs 1 to 6 with payment certificates, and the completion certificate. The test certificate has not yet been issued, and the tender specification does not appear in the list. Reuse is permitted (art. 7, Legislative Decree 33/2013) with respect for personal data. This is the Municipality's answer: we thank it for giving it on time, and we grant it the right of reply on everything below.
1. What the December 2025 variant removed
The variant originates from the RUP's order of 22 December 2025 (ref. 27563): replacing the works “financed through the Conto Termico 2.0” with compatible works. The Municipality intends to access the Conto Termico (GSE) with a proposal of €766,360.49. Determination 1610 of 30 December 2025 classes it as a non-substantial contract modification (art. 120(7), Legislative Decree 36/2023) and states that, for Notice U.0048002 of 19 March 2024, it does not require approval from the PNRR Mission Unit. The legal assessment is for a lawyer: here we report the figures. The total cost of the work remains €5,116,110.52; the completion deadline is stated as “unchanged” at 15 June 2026.
| Category removed in full | Amount removed |
|---|---|
| Heating system (basement, ground, first floor) | €172,808.52 |
| Primary air system | €120,208.09 |
| Light fittings | €67,555.30 |
| Boiler room | €60,637.23 |
| Home automation (boiler-room panels) | €24,014.74 |
| Total | €445,223.88 |
Overall the variant removes works worth €1,195,047.02 and adds €1,192,036.39 (balance −€3,010.63): among the additions, the layout of part of Largo Cherubini and of the external walkways, previously in stage 2, excluded from the PNRR. Some removed items are replaced by others in the same bill of quantities: the aluminium slat facade cladding (€164,430.00) by metalwork and painting; the rock-wool linings (€137,886.47) by plasterboard linings; the triple-pane glazing by double-pane (from 120.23 to €91.67/m²). The removed items are about 30.7% of the €3,895,694.44 of measured works in the executive design (calc.).
2. What is not in the PNRR contract
The specifications (art. 2) and the budget list three items as “works excluded from PNRR financing”, totalling €940,436.40:
| Item | Amount | What it is |
|---|---|---|
| Stage 2 | €522,416.53 | External works and square (walkways, excavation, finishes, drainage, furniture, greenery). Part was brought into the contract by the variant. |
| Demolition of the INPS building | €64,280.64 | 2,463.75 m³ |
| “Improvement works” | €353,739.23 | In the bill of quantities it is the total demolition of the old school (4,650 m³ of reinforced concrete, 9,481.5 m³ of masonry). They are not the improvements offered in the tender. |
The car park on the old school's site, after demolition, will be built by the Municipality “with additional funds” (variant report, p. 23). On trees, the report states 23 trees removed, 8 new ones in the design and 35 to be planted by the Municipality “in other public areas”, with no place or date; drawing B_06 and the bill of quantities give 11 new trees (8 maples and 3 prunus) where the report cites 8. In the documents received, 9 removals are accounted for already at SAL 1 (up to 19 November 2025), unchanged until SAL 6; no plantings are accounted for up to SAL 6. A possible, harmless explanation: the plantings are the Municipality's responsibility, outside the contract, or planned at the end of the works. When and where remains to be asked.
3. From the feasibility design to the executive design
- Underground car park and link to the other school: included in the PFTE (2023), removed after the RUP's request of 27 October 2023 because of archaeological importance and protection of the historic walls; replaced by 16 surface spaces (4 for disabled users).
- Gym: the PFTE provided for “roof and technical installations of the sports gym”; the executive design says that “the gym is of the existing type” and that pupils will be transported.
- Building footprint: moved by about 7 m to preserve the Lebanon cedar.
4. The technical bid and the executive design
The company was the only bidder (technical score 53,700 out of 70, rescaled to 70: report no. 3 of 6 September 2023). We compare the improvements in its report with the executive price list, the variant's bill of quantities and SAL 6. “No item” means that no matching terms appear in the price list: the same function might be described in other words or sit in the reports. This must be asked of the Municipality.
| Improvement offered | What the documents show |
|---|---|
| Photovoltaic from 50 to 85 kWp, 530 Wp modules | In contract 19,920 Wp (unchanged by the variant); at SAL 6, 19,795 Wp accounted for |
| Heat pumps and heat-recovery ventilation, chilled beams | No “chilled beam” item; heat pumps and air-renewal units in the executive design, then removed by the variant |
| DALI home automation, energy meter | “Home automation” category removed by the variant; no energy-meter item; at SAL 6, 18 DaliLux sensors (€8,730) |
| Wood-fibre insulation | No item; price list has polystyrene and rock wool |
| Windows with triple glazing and acoustic film | Triple glazing in the executive design, replaced by double glazing by the variant; no acoustic film |
| 2 public lifts | 1 lift (€40,568.66), unchanged |
| Multimedia totem | Item present (AP_14) only in the stage 2 bill, which is excluded |
| Bike and scooter stations; self-cleaning toilets; pet area; movable partitions between classrooms | No item in the price list |
| Tactile paths, tactile plates, Braille | In the contract (€24,928.12), but no item in the category accounted for at SAL 6 |
5. The latest progress statement: SAL 6, 13 July 2026
Works accounted for €3,313,091.71 (€3,300,421.46 net of discount) plus safety €185,010.05: €3,485,431.51, i.e. 85.3% of the post-variant contract; €601,291.91 remained. Comparing the variant's quantities with SAL 6 (automatic matching by description and price: 201 items out of 208), there are 111 items not accounted for (€317,694.72) and 77 partial (remainder €459,744.74); 44 items are already above the variant's quantity (excess €194,396.27, normal in a measured contract).
Note: this is a snapshot fourteen days before the end of the works. The items not accounted for are mostly finishes, external works and installations, plausibly carried out in the last weeks: it cannot be said that they were not carried out. Among the most significant: disposal of demolition waste €69,647.72; 33 internal doors €47,190.00; plaster €33,044.43; tactile paths €24,928.12; external lighting about €26,236.75; underground services about €30,942.55. Partial: stoneware floors 1,736.35 of 2,346.21 m²; aluminium windows 46.14 of 149.29 m²; plasterboard ceilings 23.8 of 734.4 m².
6. Dates and amounts that do not match across the documents
We do not call them errors: they are numbers that, in the documents received, do not match each other, and the Municipality can explain them.
| What | The figures |
|---|---|
| Award amount | €4,225,542.20 (works 2,961,909.86 + labour 900,000.00 + safety 264,950.55 + design 98,681.69: the sum is €4,225,542.10); executive design €4,187,992.13 |
| Safety costs | €264,950.55 in the contract; €208,841.79 in the executive design and the variant |
| Labour | €900,000.00 → €850,535.91 → €932,247.77 |
| Site handover | 9 June 2025 (report ref. 12313), 26 May 2025 (second extension), 28 December 2023 (handover of the integrated contract) |
| Duration | 488 days from handover in the contract; the 15 June 2026 deadline corresponds to 371 days from 9 June 2025 and is described in an extension as “571 days”; 488 days from 9 June 2025 would reach 10 October 2026 |
| New trees | 8 in the report; 11 in drawing B_06 and the bill of quantities |
The 15 June 2026 deadline corresponds to the company's supplementary schedule shared with the PNRR Mission Unit (ref. 10122 of 15 May 2025). The extensions by the Responsible for the procedure (ref. 14571 of 11 June 2026, 15 days; ref. 15847 of 26 June 2026, 27 days, deadline 27 July) and the partial suspension report of 12 June 2026 are motivated, in the second extension, by “unforeseen critical issues that emerged during demolition of the building being replaced”. Completion is certified on 27 July 2026 “except for minor works”, with thirty days, then another thirty (works management note of 13 August), until 25 September 2026.
Questions to the Municipality
We send them as a supplement to the request; we publish the answers, or the silence, with the date.
- SAL 7 (if issued), final account, as-built state, list of the “minor works” assigned on 27 July and 13 August 2026 and the report verifying completion at 25 September 2026.
- The partial suspension report of 12 June 2026 in legible form and the resumption report; whether demolition of the old school was completed and with what funding.
- The Conto Termico 2.0 documents (proposals ref. 27433 and 27682 of December 2025, €766,360.49 framework): award, company, amounts and dates of the works replacing the boiler room, air conditioning, primary air, home automation and lighting.
- Whether the improvements in the technical bid that are not in the design (85 kWp photovoltaic, chilled beams, energy meter, wood fibre, two lifts, bike stations and others) were subject to a conformity check against the bid, a price reduction or a formal waiver.
- Test certificates (technical-administrative, structural, acoustic) and energy certification.
- Trees: the agronomic survey, the date of the removals, and the place and date of the 11 planned plantings and the 35 trees to be provided by the Municipality.
- A reconciliation of the amounts and dates in section 6 (award, safety, labour, handover, duration).
- The tender specification, not included in the list of documents transmitted.
Figure → source
| Figure | Source |
|---|---|
| €445,223.88 | Comparison table A_19_VAR pp. 56-57 (sum of five categories) |
| €1,192,036.39 / €1,195,047.02 / −€3,010.63 | A_19_VAR p. 59, “Summary” |
| €4,086,723.42 / €4,089,310.44 | A_18_VAR p. 3; determination 1610/2025; A_01_VAR p. 26 |
| €766,360.49 | Determination 1610/2025, p. 3 |
| €940,436.40 (522,416.53 + 64,280.64 + 353,739.23) | Specifications A_09 p. 7; budget A_06; bills A_05_a.2, A_05_c, A_05_b |
| 3,313,091.71 / 3,300,421.46 / 185,010.05 / €3,485,431.51 | Payment certificate no. 6 of 30/07/2026; SAL 6 p. 106 |
| 27/07/2026; 25/09/2026 | Completion certificate; works management note of 13/08/2026 |
| 19,920 Wp; 85 kWp | A_19_VAR item 173; technical bid, point C.2 (p. 8) |
| 53.700/70, unico offerente | Tender report no. 3 of 06/09/2023 |
| 111 voci / €317,694.72; 77 parziali / €459,744.74 | OpenCivTech calculation on A_19_VAR and SAL 6 (automatic, approximate matching): data in docs/documenti_comune/SCUOLA_MAMBELLI_voci_variante_e_SAL6.csv |
| 23 abbattimenti; 8/11 nuove essenze; 35 a carico del Comune; 9 abbattimenti al SAL 1 | Report A_01_VAR p. 22; drawing B_06; bill of quantities; SAL 1 and SAL 6 |
Last updated: 6 October 2026. Right of reply: we publish in full the answers of the Municipality, the company and anyone cited. This dossier is not legal advice.